|
Client
City
of Bristol
Department
of Public Works
Location
Bristol,
Virginia
Performance Period
1990-Present
Services
Design
engineer including geotechnical, civil, hydraulic, and environmental
engineering analysis and preparation of plans and specifications
Groundwater
Consulting including modeling, monitoring, analysis, and reporting
Construction
Field Services, including QA/QC, Contract Administration, and
documentation
Operations
Engineering, including equipment selection, operations safety,
operations plans
Project Scope
STS
was hired by the City of Bristol to convert a former limestone
rock quarry into an 8,000,000 CY municipal waste landfill having
a 6 acre base footprint. The quarry is 300 to 350 feet deep and
has lateral dimensions of 600 feet by 2,000 feet.
Since 1990, STS engineers have successfully
taken the project from concept through a dual permit approval
process with the Virginia Department of Environmental Quality,
design, construction, and Phase I operations start-up.
The development of the quarry
presents several unique challenges. The first of these is stabilization
of the steep sidewalls to limit and contain rock falls. This
is being accomplished via a combination of rock bolting, rock
scaling, draped mesh and wire rope net, and placement of rock
fall protection fence along the existing haul road. The stability
of the rock walls was evaluated utilizing detailed geologic mapping
of the rock faces in combination with stability analyses, rock
coring and laboratory testing.
The second challenge is the seepage design
of the liner system for the sidewalls. While the liner design
for the quarry base is a relatively conventional composite clay/geomembrane
liner, the approved sidewall liner incorporates the draped wire
mesh along with a protective layer of geotextile, PE geomembrane,
and a geocomposite drainage layer. A buffer zone is used between
the waste and the liner system to protect the liner. The liner
design included material investigations to determine borrow sources
for the clay liner.
A third challenge is handling of groundwater
infiltration. The design incorporates a drainage control layer,
which captures seepage and conveys it to a discharge location.
Seepage analyses indicated that this will maintain the existing
inward gradient, which effectively makes the discharge location
the down-gradient monitoring location for the landfill.
The project design also included the design
of 9 to 14 foot diameter tunnels and raised bore shafts to accommodate
leachate and storm water facilities. A 0.5 MGD leachate storage
tank was also included for storage of leachate during peak storm
events.
STS subcontracted the design, permitting,
and design oversight of the 800 TPD baling facility/transfer
station, which is part of the Phase I initial startup development.
Mattern and Craig, from Roanoke, Virginia performed the engineering
on this portion of the project.
Construction on Phase I of the project was
completed in early 1998. Landfill Operations were transferred
from the existing facility to the new facility on March 2. STS
is providing operations and construction consulting services
for the new facility.
Unique Issues
- Unique physical setting presenting challenges from an engineering,
construction, and operations standpoint.
- STS has worked closely with the Owner, contractors, State
regulatory personnel, and subcontractors to develop an innovative
approach that has proven to be successful in a very unique setting.
- The Owner is extremely pleased with the operation to date
and is anticipating future expansions in the short term.
Client Benefits
- STS's expertise has allowed the Owner to complete a challenging
project that had many potential pitfalls associated with it.
- Our field personnel helped keep the project on schedule during
the Summer of 1997 to allow the City to continue to solicit new
waste contracts while construction was underway.
- The City of Bristol is now operating a unique, long-term
landfill that is viable economically for themselves and the surrounding
communities.
Back
This site, including all photos and content,
© 1998 STS
Consultants Ltd. |